Phase Timeline
1 Program Initiation Complete
2 Background Report Complete
3 Issues and Opportunities and Vision Complete
4 Alternatives Complete
5 Goals and Policies Report Complete
6 Environmental Impact Report (EIR) April 2010 - November 2012
7 Public Review of Draft EIR November 2012 - January 2013
7a Public Review of Recirculated Draft EIR July 2013 - September 2013
8 Final Documents and Adoption October 2013 - December 2013